HI Gurus,

I have a senario in which,

I have created sales order in VA01,

I have done outbound delevery VL01N, Inspection lot is generated while doing picking.

I want to disable the Post goods issue tab in VL01N so that the inspection lot is cleared and certificate is printed and then only this tab ( Post goods Issue ) tab should get activated.

Otherwise it should be activated in VL02N.

Else is there any control other than this to post the goods issue so that the goods issue should only be done after clearing the inspection lot. Is there any user exit to suit this senario...

Thanx in advance

Praveen Kumar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi praveen,

also pl have a look at this thread.

[Inspection lot|http://www.sap-basis-abap.com/qm/inspection-lot-vs-quality-certificate.htm]

regards

sadhu kishore

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear Lakshmipathy,

Please Eloberate on your answer.

while doing VL01N, the person is doing PGI,

But the syetem is not stopping this.

The stock is posted in Quality and PGI is done simultaneously.

Please suggest

Lakshmipathi
Active Contributor
0 Kudos

Dear Praveen Kumar

If inspection lot is created while doing delivery, you cannot do PGI. Only after quality clearance, you can do post goods issue. This being the case, why do you want to disable PGI tab.

thanks

G. Lakshmipathi

Former Member
0 Kudos

Hi,

You can just put a delivery block with the reason as goods for inspection.

This will automatically create the delivery doc but you wont be able to process the subsequent processes like PGI,invoice,etc.

This can be configured in the SPRO screen or on the particular delivery header itself.