on 04-11-2008 5:28 AM
Hello
How Is it possible to extend validity period of activity types.
Thx
Hi,
Try to re-create with KL01 with the starting date being the next day of the existing end date of the activity type.
If found useful...assign points.
regards,
Sriram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear SR,
You can change the analysis period of the activity type.
KL02 - change activity type... hit enter
click on the EDIT tab on the menu... Select the option Analysis Period. A seperate window will pop up .. click on other analysis period.
Here you can change the analysis peiod of the activity type...
Hope it helps you.
Regards,
Ajay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.