In META Process chain, a local chain got failed and i rectified it manually.. after doing it manually the following step is not triggering.there are lot local chains are there after that.

can anyone tell me how to trigger the next consecutive process in the process chain to complete the whole process chain.. Is there anyother way is there other than using FM RSPC_PROCESS_FINISH..

Regards,

Gowri

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

done it manually

Former Member
0 Kudos

not solved

former_member345199
Active Contributor
0 Kudos

Hi,

Whats your mail official mail id?

thanks,

JituK

Former Member
0 Kudos

Hey i am not able to post my correct Id.. Instead of 2 use @ in my previous post

former_member345199
Active Contributor
0 Kudos

Hi,

Send it, try it and lemme know.

Thanks,

JituK

Former Member
0 Kudos

Hey Jitu,

Sorry yar.. i didnt get any docs..can you again post it to Gowrisankar.NK(shift 2)Honeywell.com

Former Member
0 Kudos

Even you can try SM64, but it'll only help if the instance is not generated and if the local chain didn't report of the failure to the meta chain I guess....

Rgrds,

Habeeb

Former Member
0 Kudos

Hi Habeeb,

can you explain little more elaborately.. i am not able to interrupt your information....

Former Member
0 Kudos

Chk this

/people/siegfried.szameitat/blog/2006/02/26/restarting-processchains

Regards,

B

Former Member
0 Kudos

Hi,

Another way to continue with the data loads is to create a copy of the part of the chain which you want to continue and start it.

1)Use =copy tcode to create the copy of the process chain

2)And then remove the part which already completed sucessfully,

3)then create a temporary Start variant, save the chain as temp

4) and then schedule it to start immediately.

5) When the temp chain completes, delete the chain

Hope it helps...

Cheers,

Habeeb

former_member345199
Active Contributor
0 Kudos

Hi,

Try if repeat option is working, else you have to open each local chain and trigger it manually.

thanks,

JituK

Former Member
0 Kudos

Repeat option is not working..Is it possible to trigger the event in SM64.

former_member345199
Active Contributor
0 Kudos

Hi,

I am not sure if it works or is advicable. Never tried that in such a scenario.

Why dont you use the FM ?

Thanks,

JituK

Former Member
0 Kudos

I have restricted with Transaction code SE37 & SE38...as it was related to sensitive loads.so though of looking alternate ways..

former_member345199
Active Contributor
0 Kudos

Hi,

Ok in case there is a workaround to run that FM is it possible for you to try it ?

thanks,

JituK

Former Member
0 Kudos

ye Jitu..can you tell me how to do that...

former_member345199
Active Contributor
0 Kudos

Hi,

Can you share you email id.

Not in public domain (yahoo, gmail,etc)

Probably offiicial id.

thanks,

JituK

Former Member
0 Kudos

Hi Jitu,

you can send docs to Gowrisankar.NK 2 honeywell.com

Thanks & Regards,