on 04-10-2008 1:10 PM
Hi all,
I have a problem in automatic data updation in PIR after changing the value of the Planned delivery time field in Vendor Master Record.
While saving the Vendor Master after changing the value of planned delivery time, a pop up window will appear saying it automatically updates the value of the same in PIR & Material Master data.
But the value remains the same in PIR.
Please help me on this issue.
Points will be rewarded
ragards,
hi raju
Just check kishore's statement,if you are able to get the update in Info Record then fine OR check the settings for Auto info record update in Customising.
Can you tell me the advantage of updating Planned delivery time in VMR rather than updating in PIR & MMR ??
Thanks
Kamath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
The Planned delivery time in the PIR gets updated once the PO has been raised on this Vendor.
Please check the same after creation of PO.
Thanks & regards
Kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.