External Requirments ;- Wrong Purchasing Group

Former Member
0 Kudos

Hello SRM folks,

We are on SRM Server 5.5 with ECC 6.0 classic scenario. We have external requirments ( Purchase requisition in ECC) coming to SRM sourcing. The issue I observed that they always come up with one purchasing group. We have mapped all the purchasing group in the PPOMA_BBP.

Any idea why the SC in sourcing always the same purchasing group.

Thanks,

Pradeep

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello,

The default settings value for Purchasing group works in the following

way : the correct purchasing group is determined on the basis of the

product category. And this information you can find out in the

organizational responsibilty in the PPOMA_BBP

( i.e. which purchasing organizations can potentially procure for the

department user). Also in the product responsibility we maintain which

product category(s) the purchasing organization is responsible. And if

system finds several purchasing groups that are responsible for the same

department and the same product category it will take the first one in

the table. You can confirm this behavior by changing the product

category in the default setting and you will see that it automatically

adjust the correct purchaing groups.

I hope this informations answer your enquiry.

Thanks and Kind regards,

Gaurav

Former Member
0 Kudos

Gaurav is right,

As per the standard system behaviour, while transferring external

requirements the system always does a new determination of the purchase

organization data in the SRM system.

The backend purchasing group value

is not part of the interface and it is not passed to the SRM system

along with the purchase requisition as per the standard design.

To change this behaviour

i.e. if you want the ECC PR to go to worklist of the purchaser maintained in ECC PR

you need to employ 2 BADIs

BBP_PGRP_ASSIGN_BADI

BBP_DOC_CHANGE_BADI

we have done it

BR

Dinesh

Former Member
0 Kudos

Hi Dinesh/Disha,

Thanks for your reply. Do I need to implement both (BBP_PGRP_ASSIGN_BADI

and BBP_DOC_CHANGE_BADI) Badi Or only BBP_DOC_CHANGE_BADI.

Since we have maintained the same code for purchasing org and group in SRM and ECC system. We want to change the SRM SC purchasing org and group based (Implement BBP_DOC_CHANGE_BADI and making RFC call to the backend and passing purchase requistion and get purchase org and group) on ECC purchase req purchasing org and grp. This will also enable ECC PR to go to worklist of the correct purchaser/purchasing group.

If you have done the same could you please share the sample implementation for the same.

Thanks,

Pradeep

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

You just need to implement the badi "BBP_DOC_CHANGE_BADI".

See the solution in the foll threads:

BR,

Disha.

Former Member
0 Kudos

Hi Disha,

Thanks but the below sample code does not look for the purchasing org and group information in ECC based on purchase req. I am thinking to get the PR no in the ite`m table i.e.it_item-ext_demid will have the PR no.Then make an RFC call to R/3 to get the PR deatils like P org and Pgrp etc. And update the same in the SRM SC.

Could you please provide some details.

Thanks

Former Member
0 Kudos

Hi Pradeep,

Your approach is right.You need to make an RFC call to get the deatils for the PR.The links in my reply are for the sample code to be put in the SRM badi.But,yes if you need ECC specific data,you need to make an RFC call to ECC.You could use the FM "BAPI_REQUISITION_GETDETAIL" for that.

P.S. If you find the replies useful,remember to say THANKS in the SDN way!

BR,

Disha.

Former Member
0 Kudos

Hi,

You can change the Pgrp in the SC.

See the solution in the foll threads:

BR,

Disha.

Do reward points for useful answers.