Hi Experts,
I have set up the back-to-back process whereby a purchase requisition is automatically created after I save my sales order.
My schedule line category does not have any ATP related checks. However, I keep getting the ATP screen in the sales order and the system proposed a later delivery date with confirmed quantity.
In the material master, the availability check is KP (no check). The material does not have MRP views.
I want the system to confirm the quantity on the requested date itself.
Why does the system proposed another delivery date with confirmed quantity when I have already turned off the availability check in material master?
Appreciate if some experts could throw some light on this.
Thanks,
HweeLing
Hi,
Just turning off the availability check in material master, doesnt stop the sequence of the requested delivery date.
Just go through this info.
Checking Rule
You use the checking rule to control the scope of the availability check for each transaction in sales and distribution. You also specify whether the check should be carried out including or excluding replenishment lead time. The individual checking rules define by transaction, which stock and inward and outward movement of goods should be taken into account for the availability check.
Schedule line category
You can control with the schedule line category whether an availability check and transfer of requirements should be carried out in the sales documents. The possible settings for this at schedule line level are dependent on the settings in the requirements class which is determined from the requirements type of the material.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I found the right solution.
The purchasing GR time was set to 2 days in SPRO.
I have removed the 2 days and it is working fine now.
Thanks anyway.
Points rewarded for helping 😃
Cheers,
HweeLing
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear HweeLing
First go to OVZH, select Requirement Type LSF (if you are processing MTS) or KEK (if you are processing MTO) and make a note of what value is maintained in Requirement Class.
Now go to OVZG, select the above Requirement Class and untick "AvC".
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.