Hi guys,
After transfering material master from ECC to APO
Checking horizion and ATP group not matching with ECC data .
For example i have planned delivery date as 50 days where as checking horizon is 20 days in APO , Could any one explain me the route cause for this?
Thanks and regards
Thamizhchelvan G
Old Thread.
Answers given seem to be correct.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Thamizhchelvan,
Here is summary of data mapping between ECC vs APO for PDT and Checking Hrz.
1)Planned delivery ( in ECC MRP2 ) = Planned Deliv. Time ( in APO Procurement Tab)
2) Checking Hrz. :-
 Total replenishment time = Checkg Horizon
 If Total replen. Time is not maintained
- For Inhouse production Checkg Horizon = In house prod. Time + GR time
- For Externally produce Checkg Horizon = Planned delivery time
Hope this will help you.
Reward points are welcome.
Regards
Samir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thiago
This is standard behaviour. Checking Horizon is calculated as follows -
For Procurement Type E or X - Total Replinishment Lead Time
(or if Total Replinishment Lead Time is not maintained, In-House Production time)
For Procurement Type F- Planned Delivery Time + Goods Receipt Processing Time + Purchase Processing Time (for plant if maintained in Tcode OMEW).
Rishi Menon
Little surprising why planned delivery time and checking horizon are different. Usually planned delivery time from ECC comes into both those fields. Reasons why they could be different -
1) CIF user exits that may be disallowing updates to one of those fields
2) Change transfer not setup on ECC side (BDf9 --> CIFMAT --> check if planned delivery time is setup for change transfer)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Thamizhchelvan,
Here is the explaination why you see differences.
Following are the mapping of data ECC vs APO
Planned delivery ( in ECC MRP2 ) = Planned Deliv. Time ( in APO Procurement Tab)
Total replenishment time ( in ECC MRP3) = Checkg Horizon ( in APO ATP Tab)
Hope this will help you.
Regards
Samir