Material master transfer

Former Member
0 Kudos

Hi guys,

After transfering material master from ECC to APO

Checking horizion and ATP group not matching with ECC data .

For example i have planned delivery date as 50 days where as checking horizon is 20 days in APO , Could any one explain me the route cause for this?

Thanks and regards

Thamizhchelvan G

Accepted Solutions (0)

Answers (3)

Answers (3)

wilian_segatto
Employee
Employee
0 Kudos

Old Thread.

Answers given seem to be correct.

samir_ali
Participant
0 Kudos

Hi Thamizhchelvan,

Here is summary of data mapping between ECC vs APO for PDT and Checking Hrz.

1)Planned delivery ( in ECC – MRP2 ) = Planned Deliv. Time ( in APO – Procurement Tab)

2) Checking Hrz. :-

 Total replenishment time = Checkg Horizon

 If Total replen. Time is not maintained

- For Inhouse production Checkg Horizon = In house prod. Time + GR time

- For Externally produce Checkg Horizon = Planned delivery time

Hope this will help you.

Reward points are welcome.

Regards

Samir

Former Member
0 Kudos

I got the same mistake here...

Although, my field total replenishment lead time is populated (MRP3 - WZEIT), the product data is filled with the rule:

For Procurement type E=Replenishment Lead Time, F=PDT+GR Processing Time

Did it happen with you ? Did you find any note?

Regards.

Former Member
0 Kudos

Thiago

This is standard behaviour. Checking Horizon is calculated as follows -

For Procurement Type E or X - Total Replinishment Lead Time

(or if Total Replinishment Lead Time is not maintained, In-House Production time)

For Procurement Type F- Planned Delivery Time + Goods Receipt Processing Time + Purchase Processing Time (for plant if maintained in Tcode OMEW).

Rishi Menon

srinivas_krishnamoorthy
Active Contributor
0 Kudos

Little surprising why planned delivery time and checking horizon are different. Usually planned delivery time from ECC comes into both those fields. Reasons why they could be different -

1) CIF user exits that may be disallowing updates to one of those fields

2) Change transfer not setup on ECC side (BDf9 --> CIFMAT --> check if planned delivery time is setup for change transfer)

Former Member
0 Kudos

HI srinivas,

Could you explain me what setting i suppose to check , i do not get you please.

Thanks and regards

Thamizhchelvan G

samir_ali
Participant
0 Kudos

Hi Thamizhchelvan,

Here is the explaination why you see differences.

Following are the mapping of data ECC vs APO

Planned delivery ( in ECC – MRP2 ) = Planned Deliv. Time ( in APO – Procurement Tab)

Total replenishment time ( in ECC – MRP3) = Checkg Horizon ( in APO – ATP Tab)

Hope this will help you.

Regards

Samir

Former Member
0 Kudos

Hi Thamizhchelvan ... ,

If you have not entered a total replenishment lead time in the sap system, for a product procured externally. the planned delivery time is adopted in the checking horizon ( APO) at the time of the transfer.please check once again and let me know