I am new to this forum, and i seen all the Q's and solutions from the exports, these are very good for learners like me
HOW CAN WE DO AUTOMATIC UD (No usage decision for In-process Inspection lots) for in-processed Inspection lots
when i am doing from QA32, After results recoding and automatic validation status of the lot is converting
from REL CALC ORRQ to INSP DEF ORRQ and lot will be remain for UD plz help me on this issue..
Thanks & Regards
Vattijonnala
Hi Vattijonnala,
For automatic UD the plant dependent QM setting at plant level need to be maintained (Waiting time (hrs))
In the t-code QA10 we can get the list of the insp lot for which result recording is done & UD is not done.
you can set a batch job to run this .......T-code QA17
Do let me know if you have any further query on the same.
Reward points if you find this information helpful
Regards
Kaushik
Edited by: Kaushik Choudhury on Apr 9, 2008 12:38 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.