Dear Sir,

In repetitive mfg. i m using T-code MFPR

PLease give me the next steps?

Points will be rewarded

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member204463
Active Contributor
0 Kudos

Hi Sonal,

In REM, you need to use the inspection type 13 to be activated in the material master QM-view. Also, you need Production version for the material MRP4 view. Goto MFPR, give material, Production verion and plant. Drill down the line item and select the material and click on Create Inspection Lot. Inspection lot will be created. Inspection Lot size obtained will be that of the value which you`ve specified in the production verion. Goto QA32 do results recording and take usage decision asually.

One thing you need to note is that only one inspection lot can exist for a combination of material , PV and plant. New lot can be created only after UD has been taken for earlier lot.

Reward if cleared and close the thread.

Keerthi