Hi,

We have multiple production version scenario for the same Production bookable Assy. We have rolled up the Cost for this Assy by using mixed strategy. However, we are unable to release the cost for this Assy as Marking is not allowed.

Also, how can I ensure that all the down level Assys can be Cost released which are with mixed costing & without mixed costing.

Please explain in details.

Regards,

Vivek

9881061972.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

If you want to cost the assembly which is multilevel, you have to use CK40N instead of CK11N.

Pl. try this.