on 04-07-2008 3:02 PM
Hi
When creating master recipe and BOM, is there is any way to fix a formula in such a way the system should calculate the procudt qty from the item qty.
Pls clarify...
JK
Hi
you may use material quantity calculation to achieve this. Have a look at the help files: http://help.sap.com/saphelp_erp60_sp/helpdata/en/05/603bc6462311d182b50000e829fbfe/frameset.htm, then Process Orders > Material List Components > Material Quantity Calculation. See the "Example: Calculating Product and Component Quantities".
Good luck
Eivind