Budget availability control to be activated from PO onwards

Former Member
0 Kudos

Hi gurus

I want availability control on budget not to be checked on PR,but from PO onwards.Please help me in this regards

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You need to define the Availability-control activity group of configuration to restrict budget consumption. As per standard all acitivity group will be there. You need to define as per your requirments. Refer the below path.

Project System--> Costs --> Budget -->Define tolerance limit

Regards,

Rakesh Pradhan