on 04-05-2008 9:57 PM
Hi.
If I create a Res for WBS element and executed the MRP with t-code MD51, after checking the PR, I notice that the PR does not show a price, this only happens when creating the PR with MRP. But if I create the PReq + Res WBS element it will show a price.
Any tip where to look?
Best Regards...
Juan Carlos Rivera
Are u using same material in both cases ? ( MRP run and Manaual assigment) ? ..
Please verify MRP 2 and MRP 4 views of the material. and can try with some other material to check whether the issue is material specific or not? if yes....than cause of issue is material master settings.
please post yur findings.
thanks
saikishore ganga.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The parameters on MRP where ok, the problem was caused by the cost asigned to the material on the plant, because the PR takes this value when is created by the MRP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.