i have a problem while doing customer returns in VL01N (PGR).system displays error msg.
E VL 171
Status of inpection lot xxxxxxx / partial lot 00000 does not allow goods issue.
Material having inspection set up on material master with inspection type-06
can u tell me how to solve this.
thanks in advance.
Dear Prakash
It is because in Quality view of material master, inspection type 06 has been asssigned which is "Inspection for returns from customer". To clear this quality, go to QA32 and clear the lot. You need to check with your quality people.
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi prakash
In MMR i think you must have assigned a quality inspection as 06 . so at the time doing delivery , and before PGI , quality inspection took place. Now when you are doing PGR , i think you just check the goods insepction data at item level in delivery data . and remove that quality inspection 06 and then save it . then only PGR will happen .
Because you have assigned qualtiy inspection in MMR , system is checking , wheather the goods are good or not .that could be one of the reason it is not doing PGR, if u remove that 06 which is goods inspection then PGR will be done , then you can proceed further
Prakash if you have done in adifferent way plz share with us and if it got solved also plz let us know
Reward if useful
Regards
Srinath
Edited by: sri nath on Apr 5, 2008 11:44 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.