Hai

Sap experts.........

i have a problem in BOM pricing........

pricing of the car at 300000/- Rs, tyre at 7000/-Rs. my client also selling tyres as independent of main item. i.e car.................

Do u make new pricing o make a new material for independent sales of tyres, if my tyre price is 80000/-Rs for independent sales

Thank u in advance

regards

anjan

Accepted Solutions (0)

Answers (3)

Answers (3)

Lakshmipathi
Active Contributor
0 Kudos

Dear anjaneyulu

With the item category NORM itself, you can maintain price for tyre in VK11 as INR 80K, so that whenever you raise sale order, the price will fetch from VK11.

thanks

G. Lakshmipathi

Former Member
0 Kudos

Hi anjaneyulu,

the scenario would pretty much work out, pl do it this way.

When you sell Car as a BOM, maintain the price at header level ie main item.

so the item cat determination would be :

OR + ERLA----


TAQ for CAR (maintain car price as 3 lakh)

OR + Normusage blank TAQ------TAE for TYRE

At VK11 maintain Tyre price as 8 k,

so when you sell tyre individually the price would 8k because the item determination this would be,

OR + Norm----


TAN (single item Tyre)

Hope it helps.

regards

sadhu kishore

Former Member
0 Kudos

hi

suppose u done BOM through Main item level then

just goto VK12 enter the tyre material number change the price save it . now whenever u raise the order for tyre the system pick up value of new price.

if u select the main item in sales order leveli.e car here car price value is Rs 3 lakh

else

if u maintain BOM through Subitem level then car value is increased by Rs 1000.

any doubt send me mail krishna2603at yahoo.com