on 04-04-2008 11:25 AM
Hi Experts,
i am facing problem when iam creating purchase requistion through CJ20n
when ever i raise puchase requisition it not updated as commit ment values . please give the settings what to be done for getting it in commitment values
Please iti is urgent
With regards
Prasanth N
Hi Prasanth,
In case you have already activated commitment management and still facing the problem, and if you are using valuated project stock, then get stock accounts involved created as statistical cost elements.
with regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Talk to your FICO consusltant/ MM consultant, if you have access to T.code OBYC settings go to the Inventory postings (Transaction BSX)
Check the valuation class of the desired material and the GL Account mentioned for them.
Ask the FICO to create those commitment cost elements (Tcode. FS00) with the Cost element cateory 90.
AM sure this will solve your issue.
Reward points if found helpful.
Thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Check your settings of commitment management in T code okkp. if your commitment mangement is not activated then activate it..
it will definately solve your problem.
Regards
Lallan Singh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ensure that commitment mgt is active under the controlling area using T Code OKKP and then execute the Program RKANBU01.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.