on 04-04-2008 11:12 AM
Hi,
In sales order we will see requested delivery date, the user required this requested delivery date is show only working day, presently it is irrespective of the working days. . ( it should not affect other sales area also)
Please suggest me if there is any config changes from which I can fulfill the requirement.
Thanks & Regards,
Sachin
Dear Sachin,
You can try with this option
Go to transaction OVXD then go to detail screen of the Shipping point here you can find field called Det.Pick/Pack Time in the Detrmine times tab there you select option as 'C' Default from shipping point now the system will determine the pick pack time based on the Factory calendar which you have assigned to the shipping point in the Times tab.
In that Calendar you can maintain the holidays.
I hope it will help you
Regards,
Murali.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear sachin
Go to TCode SCAL, and there you can define number of working days and holiday at bottom of the checkboxes. If you untick Saturday and Sunday, your requested date will flow accordingly.
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can restrict factory calender per plant wise or shipping point wise. But U cant restirct that to sales area wise. So maintatin factory caledner as per your requirement and then assign it to plant for which u want delivery date should be working day wise..
regards
Sankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.