on 04-04-2008 8:34 AM
Hi!
We have an extended classic scenario already up and running between ERP->EBP system without XI usage.
Now it is necessary to configure SUS integration for ASN creation purpose. As I can see SAP has 2 standard configuration guides: one for SUS-MM and another one for SUS-EBP, but they are not fully relevant for ECS.
Could anybody tell me please from what system EBP or ERP it is better to send PO to SUS system when we are using extended classic scenario? And what are advantages/disadvantages of this?
Thanks and Regards,
Siarhei
since you have ECS already in place for PO creation
yr leading PO will be in EBP and can be changed in EBP only
ECC will only receive a copy
Normally business will like to send the PO changes to SUS also
hence you may have to employ EBP-SUS compulsory
just check this with yr business client
BR
Dinesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dinesh!
Thank you for your answer! It is clear that leading PO is in EBP, but why I can't use ORDERS and ORDCHG IDOCs to transfer PO and PO chnages to SUS?
One other question: do you know whether Configuration Guide for ECS exsits (like SUS-MM and SUS-EBP documents)?
BR,
SIarhei
Edited by: Siarhei Tsikhanenka on Apr 4, 2008 9:56 AM