hi fi experts
can anybody tell me how asset accounting will be integreate to the project system
can u pls give me the clear information
regards
venkataswamy
Hi Venkataswamy
The integration is that you collect the cost for an investment on a Project (WBS) in the project you can do budgetcontrole. You create (from the project) an asset under constuction.
Every month you run a settlement for investment projects, this is then settled to the asset under construction. When the project is completed you can do a settlement from rhe AUC to the final asset and close the project.
Based on the coselents it is possible to to post a part to an AUC and an other part to costs..
Paul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.