Hi QM Experts,
I have a question about the rework order.
For the original order i use inspection type 03.
After found the defect, i create the rework order using CO07.
My question is how to create the inspection lot to check the rework order ?
Thanks in advance,
Helly
Hi
You have activated inspection type 03 .
But For inapection type 03 , the requirement is to have inspection charactristics & control key used in routing sholud allow inspection.
But here you have created the rework order in Co07.This is with out material & must be with reference operation set.
Pl. go through the order in operation overview screen whether controlkey allows inspection or not.
In the reference operation set also you should have assign inspection charactaristics or not.
Pl. chk.
Regards
YMREDDY
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Helly,
I guess you are using a specific order type for the 'Rework'. Check the configuration under IMG:
Quality Management > Quality Inspection > Inspection Lot Creation > Inspection for Manufacturing Order.
For your plant/order type combination check assignment of 'Inspection Type' on the 'Planning' tab (it's near the bottom)
Hope that helps.
Colin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.