Dear all

Facing problem after Changing "Inspection point" of material.

There are different Plants and materials.So i create a new inspection point and add it in Routing of One materials in one Plant .After this when new inspection lot of that material generated and data is saved in new inspection point then the same inspection point is displayed in all material in all plants.

So the problem is by changing inspection point of one material it displayed in all mateial in all plants.How to aviod this problem? So new inspection point only reflects in one material not all material in all plants.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

Pl. understand the cocept of functionality of " Inspection point ".

This functionlity will be used for inspection type 03 or13.

This is inprocess inspection .

Inspection point can be freely defined inspection points

or time based inspection point if you want to inspect the samples based on the time

Or quantity based , if you want inspct the samples based on out put qty of material.

This is not based on the plant.

These inspection points will be assigned in respective routing for the material.

You have to use these points according to business requirement.

Hope it is clear to you.

Regards

YMREDDY