mark percentage complete in item

Former Member
0 Kudos

well i try to elobrate my question.in apo if A is a header item and B is its child item in 1:1,if we apply material constraint for taking planning run in ppds-apo,suppose we have req of A as 1000,system will not start till B is 1000,by someway may i put some % in item,like A can be started even if 50%of B is available.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Vikas,

System makes sure that the any PPM will only be considered if the requirement is above the Minimum Lot size. And to propose the production of this quantity, system will check the availability of the APO relevant materials in Full.

Whereas the following are the workarounds:

1. If the planning of the input material(B) is not required in APO i.e. if the planning Run(MRP Run) is sufficient for that material. You have to delete that material in the PPMs in APO. This way system will not check the availability of this material.

2. Reduce the Min Lot size in the PPM if the production of lesser quantity is practically possible or in simple terms if the Planned order of lesser quantity is acceptable.

Hope this will solve your Problem.

Do reward points if helpful.

Regards,

Manjit

Edited by: Manjit Pahal on Apr 2, 2008 3:23 PM