on 04-02-2008 6:59 AM
hI,
While crating delivery,system showing error that,
Check whether the order item to be delivered contains confirmed schedule lines.
how i can solve this issue.
Thanks,
RAj.
hi friend ,
Goto va02 then get inside the item schedule line and a tab of shipping is there beneath , check the material availability date and the traspotation planning date .
In the initial screen of delievery VL01n make the selection date which is after the date dates in the sales order..
Reward if it helps
Regards,
Aditya.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Goto VA03 - open the corresponding order and double click on the item and check for the confirmed quantity and delivery dates in the schedule.
Thanks,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.