Actual cost is not flowing in the report

Former Member
0 Kudos

Hi Friends

I am confirming the activity ( internal and external type) but actual cost is not flowing when I check in the reports.Please guide me if I am missing anything in configuration or elesewhere.Please tell me about settings in spro for this.

Rgds

Rahul M

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Please check the following details which may solve the issue.

1. Assignment of activity type, workcentre to network activity

2. Maintining acitivity rate in KP26

3. There should be activity assigned network.

Regards,

Rakesh Pradhan