Hi: everyone

I want to limit order MOQ when creating sales order (order type OR). however, sap cannot do that even if I set rounding profile, or rounding value, or mixmum value in MRP view of material master data.

for lead time, when running ATP check, sap give me a delivery proposal. I want the "delivery proposal" is mandatory. that means user cannot change the delivery date manually.

thanks

Henry

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi: Everyone

MOQ store in "sales 1" view not "MRP" view, and change message type v4082 from w to e via t-code OVAH.