on 04-01-2008 10:43 AM
Hi Friends
I have created a project and under WBS I added one General cost activity.Now after releasing the project I confirmed the activity(entered required cost center and value in RS.)
Now after confirmation of activity when I am going to check the Edit---Plan/Actual Values,
the report is not showing the actual values.
Pls. guide me if I am missing anything.
Rgds
Rahul M
Hi,
general cost activity can be used for planning purpose. Actual costs should be posted thru financial transactions only. By confirming the general cost activity you can't see the costs in actual costs report.
Thanks
Kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.