Hi,
There are two questions need your help about TRM Task and Resource management.
1. I have set up the TRM Site Notes Zones Rsource type Resoure element ... but i don't know how to create a task, For example , when i create a TO that not be confirmed, but i can't see any information from the TRM monitors.
2. After i access the TRM system by T-code LP00, i find all the transactions will relate to Handling unit , my question is Must be necessary for TRM?
Thanks for your help.
Best Regards.
Boxer Du
Hi,
you need to setup the TRM relevance
First assign the site to a Whs
SPRO/LE/WM/Interface/TRM/assign site
Second, the movement relevance
SPRO/LE/WM/Interface/TRM
Third in case the document is trm relevant,
Some work is necessary to create the taks in Urgent mode see BAdI CHANGE_TO_REQUEST
This will create task at TO creation time.
Four: Make sure you have setup the 2 step confirmation
reward points if helpful
Alain
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
no. 1) I have nearly the same problem as you have. I have also create an TO (not confirmed) and I don't see it in the TRM-monitor. It would be nice, if someone can help us.
no. 2) I don't think, that you need all transaction. You can delete some of them in the Customizing.
regards
Death_Eye
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
10 | |
10 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.