Triggering Project Sytems from Order

Former Member
0 Kudos

Dear all,

plz give me some inputs and what r all configurations required to trigger PS from Sales Order

thanks way in advance...

suresh s

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Triggering a project from Sales Order is called Assembly Processing.

It requires Standard WBS, Standard Network, Material Allocation  to the network etc ......

former_member186385
Active Contributor
0 Kudos

Hi,

CN08 is main transaction where you will trigger project system from the sales order

regards,

santosh