Puchasing for specific Project


We have our regular Product say X.Now our R & D Department developing new Product say Y,Z,whose production is also along with regular production of X.

We have requirement that I should know cost of Purchase Order raise for Product Y AND Z.For that presently we are creating Purchase order by cost center due to which we can Good Receipt PO to Particular store location.

Is there any way so that I can create PO by cost center and I can good receipt it to Store?



project account assignment can only ditinguish your project stock with others. But PO with account assignment, do not keep stock in stores but consume immediately to the project.

Either you do not use project in buying and buy in specific storage location. Manage there issue to project when need to be consumed.


0 View this answer in context