Puchasing for specific Project

Former Member
0 Kudos

Hi,

We have our regular Product say X.Now our R & D Department developing new Product say Y,Z,whose production is also along with regular production of X.

We have requirement that I should know cost of Purchase Order raise for Product Y AND Z.For that presently we are creating Purchase order by cost center due to which we can Good Receipt PO to Particular store location.

Is there any way so that I can create PO by cost center and I can good receipt it to Store?

Accepted Solutions (1)

Accepted Solutions (1)

former_member201758
Contributor
0 Kudos

Hi,

project account assignment can only ditinguish your project stock with others. But PO with account assignment, do not keep stock in stores but consume immediately to the project.

Either you do not use project in buying and buy in specific storage location. Manage there issue to project when need to be consumed.

Sanjeev

Answers (1)

Answers (1)

Former Member
0 Kudos

If you use any account assignment, then the material is deemed to be considered as Consumed..

you can not choose account assignment to store the material

Former Member
0 Kudos

so what will be best way to fulfill our requirement?

Former Member
0 Kudos

First procure for stock, then issue through mvt 201 to Cost Centre or Project