HAI GURUS,

HW I CAN DO SETTLEMENT OF A PROJECT?

MY SCENARIO IS THAT I WILL DO A QUOTATION THEN MAKE A ROUGH PROJECT AND THROUGH PDM-PS INTERFACE TRANSFER BOM TO NETWORK AND CALCULATE COSTS.

THEN WHEN QUOTATION FINALES RELEASES PROJECT PR RAISES AND HAVE COMPLETED A CYCLE UPTO BILLING.

MY PROJECT DOESNT HAVE A BILLING PLAN

NOW I NEED TO SETTLE THE PROJECT HW I CAN DO THAT?

WITH REGARDS

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You have to create a settlement profile in which you have to maintain a PA structure. The Allocation structure would have the cost elements which are relevant settlement.

Talk to your FI/CO consultant, to find out where the costs & revenues should be settled to.. Generally, Customer Projects are settled to Profit Centres..

Refer to the below help

http://help.sap.com/saphelp_47x200/helpdata/en/86/98853478616434e10000009b38f83b/frameset.htm

regards