on 03-29-2008 4:08 AM
Generally what is the duration of a SNP Horizon in a Real time scenario.
Thanks!
there are no standard answers for somethign like this.
SNP usually starts where the PPDS horizon ends (though it can overlap) and ends where procurement is placed
simply said, its generally starts about the time your Production lead time and a little less (say 2 days) and ends around your procurement lead time (say 3- 5 weeks depending on what you do) and a little more
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The SNP horizon would depend on the business. It can vary from a month to couple of years based on the nature of the manufacturing/industry.
Also, depends on the functionality of SNP, the business requirements warrants.
Heuristics or CTM planning or SNP Optimizer.
Regards
Vinod
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
6 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.