0 Kudos

Generally what is the duration of a SNP Horizon in a Real time scenario.

Thanks!

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

there are no standard answers for somethign like this.

SNP usually starts where the PPDS horizon ends (though it can overlap) and ends where procurement is placed

simply said, its generally starts about the time your Production lead time and a little less (say 2 days) and ends around your procurement lead time (say 3- 5 weeks depending on what you do) and a little more

Former Member
0 Kudos

Hi,

The SNP horizon would depend on the business. It can vary from a month to couple of years based on the nature of the manufacturing/industry.

Also, depends on the functionality of SNP, the business requirements warrants.