on 03-28-2008 6:00 PM
Hi ,
I created Planned independent requirements for a material Called "TestA" in sap r/3 and moved to apo.I am unable to veiw my requirements in my own simualtive version.so i done /n/sapapo/vercop and maintained all tha parameters like category and planning area, materials, location etc and executed the transaction.It is displaying the message that " Target version already exists . should it be overwritten". they are 3 options. 1) yes . 2) No 3) cancel.If i execute NO and cancel , the transaction is not executing. so i choose Yes , the system is deleting all the previous planned material which are executed in SNP . so I am unable to see my REquirements in /n/sapapo/rrp3.what shall i do?.
second time i created Planned independent requirements for a material called "Test B" in SAP R/3 and moved to APO. I DONE THE SAME PROCEDURE what i explained before.Now i am unable to see the requirements for material "Test A " which is planned in SNP HEURISTICS IN BACKGROUND. Totally orders and stocks are overwriting, if i execute the Trnasaction /n/sapapo/vercop . please help me how to rectify this error
you can try the report /SAPAPO/VERSION_COPY_PAR (which uses parallel processing) if you want to copy only specific order categories
You may have to copy some version specific master data too
or if you like towers of hanoi, you can do a copy of simulation version 1 into version 2 and copy version 0 into 1 etc
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
. I executed the transaction what u told /SAPAPO/VERSION_COPY_PAR what u told It is showing messageThe Target version already exists . should it be overwritten". they are 3 options. 1) yes . 2) No 3) cancel. again the same problem.If i put No. the system is not executing. If i put Yes, the system is overwriting the old data. If i put cancel,the system is not executing . Y it is happening like that. can u please try in ur system .Is it any basis error .Please let me know.
Hi Alper Myumyun ,
I used the report /SAPAPO/VERSION_COPY_TRANS.a gain the same problem occuring.do u have any idea gow to rectify this.why it is not execting when i press NO. If i press YES, why it is overwritting the other material numbers forecast. do u have any idea.
I am doing some proto typing work. I have to move Planned independent Req from sap r/3 to apo for testing .once we cif the planned independent req from sap to APO ,why i am unable to view the Forecast in rrp3 .WHAT IS THE PROBLEM?
Hi,
You can link the requirements to a Key Figure in DP planning book and release the demand to SNP. The simulation version will always delete and re-create. Or, you can use the BAPI BAPI_PIRSRVAPS_SAVEMULTI to create a custom program to copy demand from one version to another.
Regards
Vinod
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
use the transaction /sapapo/tscopy. It does the same job as vercop but gives you total control. You can specify the target and source planning versions, maintain the key figure assignment and also in selection, specify the material you want to copy.
Hope this helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Visu Venkat,
Thanks for ur reply.I followed what u said. I maintained characteristics and products , location. but i am unable to enter keyfigures.which values i have to maintain in that. my job is to transfer Planned independent Requirements and should not be overwritten.category field is in disabled mode( I am unable to enter FA {planned ind ReQ} ). If u give u ur mail ID , I will the screen shot to u. so that it will help me a lot.