on 03-28-2008 2:17 PM
Dear PS gurus,
I have created a customer project;wherein i have planed cost through network activites.while run cost reports i am not able to see the plan cost in any of the reports. the activity plan/cost comparison displays the values.also in cj 40 it is showing in planned total.
But not in any of the reports.please guide me what customisation is to be needed to display the values in reports
regards
pv
Please mention a report where you don't find the plan values.
Also check the value of 'Planned costs calc' in T Code OPUV.
If you are looking at the WBS against which the network order is assigned then, ensure to check the 'Planning Indicator' in T Code OPSC.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks for that information sreenivas
i checked it out it was ok
my scenario is RRB
top WBS element is a billing element
netwrk actvty is attached to level 2 wbs elmnt
which is accnt assnmt elmnt
my problem is that planning values are not catching for
costs internal activities rest all control key is catching values for cost.For internal processing the value input goes to revenue plan.does it have any thing to do with allocation structure for networks.