on 03-28-2008 11:16 AM
Hi Friend,
what configuration step & change in material master data i need to follow so that one can use packing material in the delivery document for finished good.
Please give information about configuration steps & Fields important in material master data for the same.
Thanks
Hi,
Create the packing Material In MM01 of material Type 'VERP'
2) Create packing Instructions from TA:POP1
3) packing Determination In POF1 ... for MM Conditon type is RCPT and for SD its is SHIP.so create condtion records here.
4) In Customization SPRO-> Logistic Execution-> Shipping-> Deliveries->Define Delivery Types
In Delivery ,there is Check box for automatic packing.
regards,
Siddharth.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.