Hi all!

Whether we can update all the customizing changes in single Request number. If yes how will be the Task number.

Yuvi.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

it is not recommended.

it it better to create a single customizing request for each customizing/customizing change.

still if you want to update all the customizing changes in single Request number then a single request is created and subsequent task requests are created for each customizing/customizing change.

regards,

kaushal

Former Member
0 Kudos

Hi kausal!

If i am going for a roll-out project for a new plant can i change TR number ranges atleast (in table E070L). Whether this is recommended. If not how can defferentiate the TR numbers for the to-be rolled out plant to that of exixting plant.

Thx in advance,

Yuvi.

Former Member
0 Kudos

Hi,

change TRKORR in table E070L to give the transport numbers a new starting point.

but all new TR are generated from this starting point , (you only change the number not SIDK)

best way to identify the TR numbers for the to-be rolled out plant or the existing plant is give meaningful description

when TR is created.

regards,

kaushal

Former Member
0 Kudos

Thank you so much kaushal....