on 03-28-2008 7:15 AM
Hi,
I had created a Repair Order for a Product and via this Repair Order, system automatically created a Service Order (SM03)
I added a component (spare part) in the Service Order that has to be consumed for Service on the Product. Upon saving the Service Order, system is prompting "Should a PReq also be created for component xxxxxxxxx ?"
What setting / conditions in the System is enabling this prompt in the Service Order ?
Thanks for help.
Raj
Mr. Raj,
Check the itemcategory in the component tab of the Service Order, if the Item Category is N, then change it to L.
Praveen