can any1 plz tell me diff between outline agrrement and schedule arrement

i am wrg on master contract whr the path for outlineaggr

is losgistic-s&d-sales----outline aggre

but i am not able see outline aggrement

Regards

Vinit

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

In SD outline agreements are a broader picture where it is further divided into Scheduling agreements and contracts

There is nothing to configure in outline agreements. just u have to select the type of outline agreement. You are going in the right path and u can do the configuration settings for contracts

regards

kishore

Former Member
0 Kudos

ya thanx

but i am not able to understand wht to do further

i have got blind

wht to do

mine concept for master contract is not clear

after readind fd help file also

if u have seetings or steps of master contract

plz guide me

Regards

Vinit

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

For config of master contract please check the following link:

http://help.sap.com/saphelp_erp2005/helpdata/en/dd/55fd27545a11d1a7020000e829fd11/content.htm

regards,

Siddharth.

Former Member
0 Kudos

hi vineet,

The scheduling agreement is the agreement between company and customer to supply the goods on particular dates. the scheduling agreement contain delivery dates and delivery quantity. it is relevent for pricing and will have schedulelines because items are relevent for delivery.

Outline agreement is a contract between company and the customer about either to purchase a certain quantity of material or to purchase a particular value of items. it doesn't contain any delivery dates.

so you need not to maintain the scheduleline categories. But it contain a release order. you will create a sales order with reference to this outline agreement where as Scheduling agreement is itself a order.

Former Member
0 Kudos

hi

out line agreements is a broader term used

it divided into scheduling agreements and contracts

bacic difference between these two is

in scheduling agreements we have schedulines

in out line agreements we dont have any schedulines

regards

ravi