Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Progress Analysis

Dear All ,

While doing transaction CNE5 i am getting , all planned values like plan POC,BCWS but i am not getting actual values like Actual POC ,BCWP.

Inspite of confirming actvities and making service entry sheet up to MIRO.

All other configuration settings are correct.

Is Result Analysis key is to be defined for posting of actual cost.

Former Member
Former Member replied

OK, so as I understand it...you have set the progress method to Time Proportional at the WBS element level.

But you want to use the Actual POC from Confirmations on the Network Activity level is this correct?

You have set the % complete via a confirmation on the Network Activity level - Is this correct?

If so as the help suggest..you can either set the Actual POC progress method to WORK on the Network Activity or you can use POC Weighting

But I think this may only be an option in Networks that are Activity Assigned not Header Assigned as yours appear to be.

We enter % complete in a confirmation via CJ20N or CN25

The progress method is WORK for the Actual POC and is stored on the Network Activity

Our Networks are Activity Assigned Networks not Header Assigned Networks

And we have no problems this end

Hope this helps

Steve

Edited by: captain caveman on Apr 1, 2008 2:57 PM

Edited by: captain caveman on Apr 1, 2008 3:05 PM

0 View this answer in context
Not what you were looking for? View more on this topic or Ask a question