hai gurus,

Today i'm planning to do client copy in my office.

This client copy is form production server to development server ( form 1 box to another box)

so. I will Choosing the remote client copy, that it rights?

the next step is lock the target client, how to lock the target client (development)

The SAP* id have profile SAP_ALL that it is enough or i must to add another SAP_USR, SAP_CUST AND SAP_UCUS

and the type that i will use is client-specific and cross-client Customizing and master/transaction data. I'm choose the correct type?

Anything that i must taken before doing this client copy?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Steps For SAP Client Copy / System Refresh

Before doing a client copy, you need to prepare the following :-

1. Find the source client space with the client size custom program which can be implemented using the rel. note:

Find the space of the client - '0118823'. This will give you the size of the source client.

2. If your are on Unix OS, adjust all the file systems according to PRD file system to fit the PRD client in DEV

client based on space requirements also.

3. You can do the client copy by remote or export/import client.

Remote method is not preferred if you are doing a large client copy.

Do a client export/import.

4. To speed up the export/import, use R3trans export/import for the clustered tables.

Please find the rel. notes related to performance improvements for cluster tables in OSS.

5. Do import and post processing.

Note: Export may take 10 to 20 hr. for 50gb of data

import may take 4 days and post import will take 8 to 15 hr. for 50gb of data. And it all depends on

your system performance.

Please refer OSS rel. notes for the few RZ10 parameters which needs to be set for cluster tables to speed up the process.

Note :-

If it is a fresh installation, do this --

1. SCC4 --> Create client no. and fill other details.

2. Logon to the newly created client with SAP* and PASS as password.

3. SCCL --> choose any profile (preferably SAP_ALL), source client 000 and target client <as created just now>.

4. Preferably do a test run initially to check if it can go well.

5. As a care check space in databases.

What are step and procedure to create a client & to take a client copy from source to target.

If you are copying from same system then flow the below steps:

1. Create the client in Tcode scc4.

2. Before that create a logical System in BD54.

3. Login in the newly created client with

user Name : sap* and password : pass

4. Use the Tcode sccl to copy the client.if you are not familiar with the client copy. Try a test run and then schedule it in background.

5. You can select the needed profile.

6. To view the log files use the tcode scc3.

If you are using different system then create a rfc connection in sm59.test the connection and then continue from the 1st step

You can also import and export a client. Use scc7 for importing from the client and scc8 fro exporting from the source client

What is system refresh when and why it is done?

The system refersh is nothing but the deletion of the client and replacing the data from other client. For example : you have clients 100, 200 and 300. Suppose when you want to refresh the client 100 you remove the client 100 and replace it with 200 0r 300 as per your reqiurement. Mostly the refresh of clients will be happen at the time of development stage.

System Refresh is a simplified term to Client Copy. Client Copy means copying the production client on to the quality to test the real data. As recommend by SAP this need to carried out every 3 months.

The process to carry out the same is as follows:

1. Create a client on quality system using txn scc4

2. Create a RFC between Production system and Quality System (need to create on quality system)

3. Login to the newly created client using sap* and pass as a password

4. Txn sccl to start the client copy. You can test the client copy by selecting the test run option. (test run will estimate the time taken for the activity).

Hope this helps you.

Regards,

Rakesh

Answers (1)

Answers (1)

former_member190272
Active Contributor
0 Kudos
Former Member
0 Kudos

Hi

Check http://www.sap-img.com/bc049.htm

Client copy is possible only if both the Source and Target are the same SAP release and support pack levels.

System copy guides are available in the marketplace at: http://service.sap.com/instguides according to your SAP release

Shaji