on 03-27-2008 8:21 AM
Hi Friends,
I want configuration steps of Product allocation.
Regards,
PS
Dear Prakash,
Go through this IMG path and do the configuration.
SPRO>Sales and distribution>Basic functions>Availability check and Transfer of requirements>Availability check-->Availability check againest product allocation.
For more details go through this link
http://help.sap.com/saphelp_47x200/helpdata/en/6b/2785347860ea35e10000009b38f83b/frameset.htm
I hope it will help you
Regards,
Murali.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
1.Allocation Procedure (OV1Z)
2.Allocation Object (OV2Z)
3.Allocation Hierarchy Mapping (OV3Z)
4.Define Consumption Periods (OV5Z)
5.Control Product Allocation (OV4Z)
6.Activate Allocation for Requirement Class (OVZ0)
7.Activate Allocation for Schedule Line Category (OVZ8)
8.Create Planning Hierarchy (MC61)
9.Generate Masking Character (OV7Z)
10.Modify Planning Hierarchy (MC62)
11.Allocation Procedure Assignment to Material Master (MM02)
12.List of Suitable Structures (OV9Z) This report is used to identify potential LIS information structures that can be used in the product allocation process. This report simply reads through the data dictionary and selects all the active information structures that contain the field product allocation object (KONOB) as the first field. This data can then be utilized in the mapping transaction (OV3Z) to link the allocation procedure step to an information structure (previous step).
13. Update the Planning (MC93/MC94)
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.