We are doing SRM upgrade from 3.0 to 5.0 . During upgrade , we are implementing item level workflow whereas we are using header level approval in SRM 3.0 .
I would like to know what are the implications on the work item pending in the approver inbox . I am sure this is going to restart as per item level workflow .
SRM experts , Request valuable inputs from your own experiences.
Regards
Mani
Edited by: Manikanda Ilango Sundararajan on Mar 26, 2008 3:23 PM
Hi Mani,
Don't keep the old workflow pending approval, if you are changing the workflow design during the upgrade.
This created a lot of problems when we are testing the upgrade, so we asked all the approver to approve before the cutover.
One option worked for us is all the pending shopping carts need to change to retrigger the new approval.
Hope you may use our experience on this.
Thank you
Sreedhar Vetcha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.