Backend Budget Avaliability Check in SC?

Former Member
0 Kudos

Dear All,

Does Shopping cart item checks budget avaliability for a project created in backend?

Thanks,

Anil

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Only if the WBS/Project budget availability check is activated in backend, you will have the check whenever the followon documents are created.

If you have Funds Management integrated then you will have more challenges in implementation on FICO side.

Good luck,

Cheers, Renga

Former Member
0 Kudos

Hi All,

Thank You for your answers.

I think i should be more clear on my question:

We created a PROJECT in PS module, this has WBS element.

This project is controlled by BUDGET.

Now when i create a shopping cart for the said WBS element does this CHECKS wether budget is avaliable in backend system????

Thanks and Regards,

Anil

Former Member
0 Kudos

The answer is YES;

I use in my scenario

Please reward points if useful

Thanks

Kasee Palaniappan

Former Member
0 Kudos

Only if the Internal Order/WBS Element has Availability Check Active in the Back end system.

Please reward points if found useful.

Thanks

Kasee Palaniappan

Former Member
0 Kudos

Hi,

Yes this is standard SRM functionality, all the FI validations from ECC will be happen in SRM.

Thank you

Sreedhar Vetcha