Schedule lines with no confirmed qty

Former Member
0 Kudos

The client needs schedule lines generated with no confirmed quantity please assist if itss possible

Regards

Maddy

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

you will have to create a project for the enhancement object ATP00001 through CMOD.... You can also explore the possibility of activating the availability check which will also set the confirmed quantity to zero.

Regards,

Murali

Shiva_Ram
Active Contributor
0 Kudos

Hi,

You may need to use user exit EXIT_SAPLATPC_002 to change the available quantity to zero. Talk with an ABAP'er.

Hope this helps.