what is the difference between ( single item, multilevel ) t-code MD02 and ( single item , single level ) t-code MD03 in MRP

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Single item multi level means parent level ( MD02 ) When MRP runs all depandent child matl also planned

Single item single level means only single item it may be parent or child alone planned

i hope it clarifies ur doubt

pl reward points or ask further qn

guru