Hi every one

In our company we prepare purchase orders(Me21n) with at least 5 delivery schedules for each line item.

And when we do the MIGO can this delivery dates can be automatically picked.

if so what are the required pre requisites for the configuration.

In our Company though Gr is done W.R.T Purchase order The delivery date of the same is not picked up.

Is it normally like that or can we make system to trigger the delivery schedule.Please let me know the configuration for possibility.

Kindly please respond to the above

Regards

Chaitanya

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

When you do PO and enter delivery date, its date when you want material to receive at ur location. But it does not mean vendor will exactly deliver on that day. This date may vary according to situation, he may deliver on exact time or may not. So delivery date to pick from PO is not feasible. If delivery date entered in PO does not match with GR date, what will you do?

Regards

Amol

Answers (1)

Answers (1)

Former Member
0 Kudos

Friend

Although you have more than one schedule line for a line item in PO at the time of GR it is cummulative qty of all the schedule line and thats the way it is.

I suggest Schdule Agreement with schedule line will give good control for you

ENJOY SAP

Regards