Cost center not getting updated in the "ADD. DATA" tab of the order.

0 Kudos

Dear All,

When i am generating a maintenance order from the maintenance plan, the responsible cost center in the "Additional Data" tab of the order is not getting updated.

While the work center in the plan is already assigned to the cost center.

Please suggest

Regards,

Ritesh

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You have cost centre field under Location tab & Responsible cost centre field under Add data tab.

Pl ref the help tips provided for Resp cost centre field.

Responsible cost center

Key of the cost center responsible for carrying out the order. The order is therefore organizationally assigned to the cost center.

This does not have to be the cost center to which the order settles its costs.

Hope this will helps you