on 03-26-2008 4:16 AM
Hi
I have been working on cProjects to PS integration for client server which runs on ECC6. Both cProjects and SAP objects are on the same server.
I have done required configuration settings for the scenario, also for CO scenario maintenance view determination for my project type I have selected Multilevel controlling (Structure Element, Automatic), but still PS project from cProjects is not getting created.
Is there anything am I missing ????
Regards,
Niraj Sikligar
Hi Niraj,
Have you make the assingnment of project type and object type.
In c project configuration.
e.g
Project type --> It Project Object type --> single object controling on WBS Frames --> Frame 9
--> please insure that you have activate account integration for that project type.
--> You are using same project type for while creating the project in c project.
--> OFIN_INT_ERP_PS (Object type)
-->CL_R3_OLR3_PROJECTDEFINATION (Proxy class)
STILL FACE THE PROBLEM PLEASE REPLY WITH ERROR .
Thanks
sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sunil,
Thanks for your reply.
Project type and its object type settings are same as you have mentioned.
For Object type 0FIN_INT_ERP_PS in Object Types for Object Links in SPRO, the proxy class is maintained is CL_DPR_OLR3_WBSELEMENT instead CL_R3_OLR3_PROJECTDEFINATION as mentioned by you.
and proxy class setting I am unable to change as it is in grey mode. Does it requires to change ? if so how can I change the same ?
Regards,
Niraj
Hi Niraj,
-->spro
-->Collrabration project
-->Connection to External system
-->Account integration
-->define object link for account integration
In that page you will find two object type on right side table
one for WBS elemet and another for internal order
select: 0FIN_INT_ERP_PS
Then double click on Name of classes inSAP (letf hand side dialog structure)
then change the proxy class and try again to replicate the project .
Also check project type details wether you have activated Accounting integration scenario if please activte
thanks
sunil
Hi Sunil,
I have done the setting of Object type as you have said.
Account Integration has been activated for the Project type.
But still PS Project is not getting created from cProjects in Accounting Tab in Account Assignment in cProjects.
Also I am getting message when I click on Costing Tab in Accounting :
"Internal error: Calling costing leads to exception "
Any help ?
Regards,
Niraj
Hi Sunil,
Costing variant earlier was PC02 which I changed to PS06.
But still I am unable to see PS project created from cProjects.
I was going through one SAP note # 977951, which says that..
The PS projects are created with the CPR0001 project profile.
Can you help me where this profile is maintained ?
Also I am getting error message :
Internal error: Calling costing leads to exception
Any help on this also ???
Thanks and Regards,
Niraj
Hi Niraj ,
You want to create
The PS projects are created with the CPR0001 project profile
then go to
SPRO->Project Systems-> Structures-->Operative Structures-> Work Breakdown structure ---> Create Project Profile ( T.CODE : OPSA )
I want information from you
In C project accounting tab you will get the buttons calculate and account assingnment
Thanks
sunil
Hi Sunil,
Project profile CPR0001is maintained in the transaction you have mentioned, my question was how the PS project will automatically created from cProjects??? Where you mention the project profile to create PS project ?
On Accouting Tab I am unable to see PS project created from cProjects automatically.
If you can send your email ID I can send you the screen shots of my error.
Thanks and Regards,
Niraj
Hi Niraj,
I checked your documet all config will correct just use following path
It important to define a project number which fits the customizing seetings of project edition mask in project
Step : Spro --> project system -->Structure -->oprative structures --> work break down structure --> @ Define project coding mask
In that check the aviaable project Number
The following characters are available for editing:
X for alphanumeric characters
0 for numeric characters
special characters to organize the project numbers
e.g Project coding key : SUN
Coding Mask :-000-00-00
Then you define the project defination as : SUN-100-01-00
When you define project number in c project use this mask code ( check which mask code are define in your system and use that)
and same will be created in your PS with same as project defination
Thanks
sunil
Hi
Issue resolved.
following changes reverted:
For Accounting Integration:
For Object type : 0FIN_INT_ERP_PS
Proxy class changed to CL_DPR_OLR3_WBSELEMENT
For Controlling scenario following changes doe :
Costing variant changed to PC02
Functioanl Area field made empty Earlier it was 400.
For Settlement profile 20, settlement to a profitability segment changed to : Settlement optional from Settlement not required.
Now I can see the PS projecte created from cProjects project.
Thanks to Sunil for his extended help.
Regards,
Niraj
User | Count |
---|---|
10 | |
5 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.