Raw Material Tracing


This is in continuation with my previous questions only

We have 2 subcontractors making 2 different FG's for us. Both these FG's have 1 distint material i.e. FG 1 has X & FG 2 has Y.

But there is one material i.e. Z viz used in both these FG's.

I have done all possible solutions i.e. tried with ME2O, MD04 (which shows sub req) which we can interpret. But client wants that if we give a raw material as input; output should be raw material with qty against the subcontractor where it will go so that there is no confusion between subcontractors stock....

My question is how will each subcontractor know that out of 1000 PCS of Z (viz common); 800 is for me and 200 is for other subcontractor

Please help