on 03-25-2008 2:08 AM
I will build a 3 system TMS with DEV, QAS and PRD.
But now, I have only DEV system available, and QAS and PRD system will available several month later.
And before QAS and PRD system available, the developer will develop in DEV system, so how can I build the TMS system?
with only one DEV system? or set up another 2 virtual system(QAS and PRD)?
I should make sure that the requests which created now, can transfer to the QAS and PRD system in the furture.
Thanks in advance.
Regards,
Randy
Hi Randy,
Your instincts are correct...and this is common...set up QAS and PRD as virtual systems now and change them to actual systems later.
Best Regards,
Matt