Dear All,
Could anyone advice me what is Direct confirmation in PS and how to setting up this thing.
Appreciate for your help.
Thank you.
Nies
Confirmations can be done directly in PS or by Time Sheets (CATS) etc.,
Confirm of network activities is possible if
1. activities should have status as REL
2. confirmation indicator must be set in control key.
Also certain confirmation parameters are defined in SPRO under node Confirmation->Define confirmation parameters.
Direct confirmation can be done for/through
1. Activity element
2. Collective/summary confirmation
For further details refer note 570471
Regards
Sreenivas